Back to portfolio

Pedro Construction Company

Upcoming. Business plan dated May 2026.

A builder of data centres for high-density AI compute in Mexico, to start once roughly twenty million dollars is in place. The plan, working name Densidad Crítica, asks for USD 22 million.

The idea

AI workloads need over 50 kilowatts per rack, liquid cooling and a different electrical design, and Mexico cannot build that at scale yet. The company would buy a regional contractor with critical-infrastructure experience, gaining references, bonding and suppliers on day one, then add international data-centre management. The window is three to five years.

The market

Hyperscalers have committed more than USD 7 billion to Mexican sites, led by Amazon and Microsoft. Querétaro’s grid is filling up, pushing projects to Aguascalientes, Guadalajara and Monterrey. Traditional facilities run 5 to 10 kilowatts per rack; AI needs 50 to 120, and almost nobody local can build it.

The Mexican market for data-centre constructionMillions of USD. The lighter bar is the projection.
01,0002,0003,0004,00020222024202620282030Millions of USD1,0203,450
Table
YearUSD millions
20221,020
20241,430
20261,850
20282,620
2030, projected3,450

Sources: Mordor Intelligence, Arizton Advisory, own analysis.

Who can build what, and where they areThe upper right is the target position.
LowLowMediumMediumHighHighTechnical capacity for high densityOperating presence in MexicoLocal buildersTraditional EPCsMEP specialistsJacobsTurnerAECOMPedro Construction Company
Local contractorsInternational EPCsThe target position

Entry by acquisition

A new contractor cannot bid without references and cannot earn them without bidding. The plan buys past that loop: a Mexican contractor with USD 15 to 40 million in revenue, a data centre delivered and valid bonding, at 4.5 to 6 times EBITDA, closed by month nine. Then turnkey data centres of 5 to 30 megawatts, conversions to high density, and commissioning.

The first eight quartersMillions of USD per quarter.
-50510Q1Q2Q3Q4Q5Q6Q7Q8Millions of USD
Inherited revenueIntegration costs
Table
QuarterRevenue, USD MIntegration, USD M
Q146
Q255.5
Q375
Q484
Q593
Q6102
Q7111.5
Q8111

The numbers

Year one is inherited revenue, year two brings the first own contracts, and from year three high-density work is most of the backlog. Margin turns positive in year two and settles near 9 percent.

Revenue and net margin over five years

Revenue, millions of USD

050100150200250Year 1Year 2Year 3Year 4Year 535220

Net margin

-10%-5%0%5%10%Year 1Year 2Year 3Year 4Year 59%
Table
YearRevenue, USD MNet profit, USD MNet margin
Year 135-2.5-7.1%
Year 2821.62%
Year 31407.05%
Year 418012.67%
Year 522019.89%
Use of the fundsUSD millionsShare
Acquisition of the contractor11.050.0%
Working capital6.027.3%
Senior technical staff2.511.4%
Technology and software1.04.5%
Reserve1.56.8%
Total22.0100%

Risks

Risk matrixShape and colour both carry the level.
LowLowMediumMediumHighHighProbabilityImpactCFE interconnection queueProject cost overrunsCritical equipment delaysPost-acquisition integrationTechnical staff shortageCurrency volatilitySector slowdownNew international competitor
CriticalSeriousMonitored

The critical three: cost overruns, met with cost-plus contracts in year one and weekly budget tracking; delays on transformers and switchgear, met with early orders and priority supplier deals; and the 12 to 18 month grid interconnection queue, met by hiring someone who has run it.

Team and roadmap

Four roles come first: a chief executive with operator relationships in Mexico and the United States, an Uptime-certified technical director, a construction finance director, and an operations director for BIM and commissioning. Founders hold 60 percent, investors 35, staff 5. The round closes in the third quarter of 2026; the backlog passes USD 80 million by month 24.

None of this exists yet; the plan starts the day the round closes.